Oracle has sent a force majeure notice to the developer of Project Jupiter, a vast New Mexico data centre tied to the Stargate AI buildout. The move is a warning about what could happen if power and construction delays push the site beyond its planned 2028 opening. It is not an announcement that Oracle has cancelled the project.
The notice was first reported by Bloomberg, citing people familiar with the arrangement. Reuters subsequently reported that Oracle is seeking protection against payment obligations if the campus cannot come online on time, rather than trying to leave as its principal tenant. Oracle has said Project Jupiter remains on its planned schedule, while Blue Owl Capital has said its financial commitments to the development have not changed.
That distinction matters. Force majeure is a contractual mechanism for events outside a party’s control. Sending a notice does not, by itself, establish that such an event has occurred or that a court would accept the claim. It does tell us Oracle wants its position recorded now, before a potential delay turns into a dispute over who pays for capacity that is not ready.
Project Jupiter is planned as a multi-gigawatt campus, an electricity demand far beyond that of a conventional office development. Data Center Dynamics reports that permitting and energy infrastructure have complicated the project. The commercial question is straightforward: can developers provide reliable power on the timetable promised to the companies buying AI computing capacity?
The Stargate ambition has always been about more than ordering chips. Thousands of servers are useful only when buildings, cooling systems, transmission connections and backup power are ready together. A delay in one of those pieces can leave enormous capital tied up while the intended customer waits. The New Mexico notice makes that risk unusually visible because the companies involved are among the biggest names financing the AI infrastructure race.
Oracle and OpenAI have already had to navigate difficult decisions around other data centre capacity. In March, a separate Texas expansion went to Microsoft after Oracle and OpenAI stepped back from that particular site. That does not make the New Mexico campus a repeat of the Texas deal, but it is a reminder that announced capacity and delivered capacity are not the same thing.
For now, the most accurate reading is cautious. Project Jupiter has not been abandoned, and Oracle says it is still on track. What has changed is the allocation of risk if the 2028 target slips. Investors, lenders and customers will be watching whether the site’s power arrangements and permits advance quickly enough to make the notice merely precautionary.